Two More Good Days

The cart path project is progressing nicely. The majority of yesterday was spent removing the old cart paths and prepping the areas for crushed concrete. The crushed concrete serves as the base below the asphalt.

Today the asphalt company laid the crushed concrete and started laying the base coat of asphalt. Everything is really coming together quite well.  The rerouted paths are really going to help with traffic flow around the clubhouse and provide a nice, clean look.

cart path removal
more path removal south of putting green
 
crushed concrete in place
rolling base coat of asphalt
Today my staff and I laid 2,800 ft2 of sod around the new cart path on #18 and around the clubhouse.  We also started preparing the new landscape beds that will surround #1 tee.

laying sod around #18
new path on #18 finished
Tomorrow's agenda includes more sod work and landscape bed prep.  The cart paths should all be prepared by tomorrow with paving starting Monday.