We will begin a new project on Monday, October 7th. Cart paths around the putting green, first tee, behind #9 & #18 greens, and halfway house will all be repaved.
As part of the project, we will remove the existing path from #18 and reroute it. This change will help with traffic flow and alleviate cart congestion around the first tee staging area.
We began work on the new path yesterday; we removed some brush and prepped the area for the new path. We removed about 7" of soil and will backfill the area with crushed concrete which will provide a solid base for the new asphalt path.
 |
before picture |
 |
brush removal |
 |
cart path excavation |
 |
preparing path for crushed concrete |