It has been a great start to the project.
Highlights include:
- removal of bunker sand from holes 9-13, 17, 18
- demolition of bunkers on holes 9 & 18
- coring out of new green expansions on holes 9 & 18
- stripped sod within the limits of disturbance on hole 10
- removed sod from 17 green and fairway to repurpose on green expansions and low mow areas
- removal of irrigation and tilling of 17
- flagged limits of disturbance on holes 11-13, 16