It has been a great start to the project. Highlights include: removal of bunker sand from holes 9-13, 17, 18 demolition of bunkers on holes 9 & 18 coring out of new green expansions on holes 9 & 18 stripped sod within the limits of disturbance on hole 10 removed sod from 17 green and fairway to repurpose on green expansions and low mow areas removal of irrigation and tilling of 17 flagged limits of disturbance on holes 11-13, 16 tree removal between holes 9/10, holes 9/18, east side of 10 and started tree work on hole 11