Despite 2.6" of rain, we had another productive week repairing and filling bunkers. We have completed 42 of the 54 bunkers on property.
This week, the two greenside bunkers on #8 were repaired and filled. We also completed the fairway bunker on #10, the greenside bunker on #3, and the greenside bunkers on #1.
This week, the two greenside bunkers on #8 were repaired and filled. We also completed the fairway bunker on #10, the greenside bunker on #3, and the greenside bunkers on #1.
the old sod on #8 east greenside bunker has been removed |
rebuilding #8 greenside bunker |
cleaning up old sand in #8 bunker |
#8 bunker bank sodded and ready for new sand |
completed bunker on #8 |