Week Update

Despite 2.6" of rain, we had another productive week repairing and filling bunkers.  We have completed 42 of the 54 bunkers on property. 

This week, the two greenside bunkers on #8 were repaired and filled. We also completed the fairway bunker on #10, the greenside bunker on #3, and the greenside bunkers on #1.

the old sod on  #8 east greenside bunker has been removed

rebuilding #8 greenside bunker

cleaning up old sand in #8 bunker

#8 bunker bank sodded and ready for new sand

completed bunker on #8