Skip to main content

Productive Week on the Range

We installed over 250 feet of new drainage this week on the driving range landing area.  Our focus was in front of the tee, where we ran a new drainage line from east to west.  We targeted this area first as it is one of the softest spots on the landing area.  The new line has not stopped running since we installed it Thursday afternoon.  This should help dry out the area significantly.

Myles digging out the drainage trench in front of the tee

Jr. cleaning out the trench

Brendan spreading out pea stone

new drainage line is installed and back filled with pea stone

Yesterday we started removing the dead sod from the new fairway.  Next week we will begin shaping and smoothing out the area.

removing dead sod from the new fairway

a good day's work